From a $36,000 bump-out to a $270,000+ second story
Typical 2026 ranges for home additions in Bellevue and on the Eastside: a bump-out $36,000–$90,000 (1–2 months on site), a room addition $80,000–$160,000 (3–5 months), a primary suite addition $135,000–$270,000 (4–6 months), and a second story from $270,000 (6–9 months). Design, engineering and permit review come before construction and add time on the front end.
Home addition costs at a glance
| Addition type | Typical size | Typical price | Construction |
|---|---|---|---|
| Bump-out | 50–150 sq ft | $36,000–$90,000 | 1–2 months |
| Room addition | 200–400 sq ft | $80,000–$160,000 | 3–5 months |
| Primary suite addition | 350–600 sq ft | $135,000–$270,000 | 4–6 months |
| Second-story addition | 600+ sq ft | $270,000+ | 6–9 months |
Ranges include structure, finishes and standard permits. Engineering, utility upgrades and difficult sites are priced after we see the lot. Your price is set by a written estimate after a free walkthrough.
Types of additions
A bedroom, family room, home office or a bigger kitchen.
Bedroom, bathroom and walk-in closet as one wing.
Double the living space without giving up the yard.
A few extra feet for a kitchen, bathroom or dining nook.
Turning space you already have into living space or an ADU — often the cheapest square footage on the lot.
What drives addition cost
- Foundation and site. Slab or crawlspace, slope, soil and drainage. Hillside lots on the Eastside cost more to build on.
- Tying into the house. Matching the roofline and siding, and opening exterior walls.
- What goes inside. A bedroom costs far less per square foot than a bathroom or kitchen with plumbing.
- Second stories. These often need the existing walls and foundation strengthened.
- Design, engineering and permits. Every addition needs drawings and structural review.
Permits for additions in Bellevue
Adding square footage always requires a permit with plan review in Bellevue. Additions over 3,000 square feet of new or replaced floor area fall under the city's new-house or large-addition permit. Setbacks, lot coverage, critical areas and slopes vary parcel by parcel, so we check your property's rules before we quote, then manage design, permitting and inspections from start to finish. For the rest of the Eastside, see what needs a permit; for a second unit, see our ADU guide.
Addition questions
Will the price grow once the work starts?
How do you protect our home while we live in it?
How long does a home addition take?
Is it cheaper to add on or to move?
Can we stay in the house during an addition?
Do you handle design and engineering?
Sources: City of Bellevue — residential building permits. Checked November 2026.