How long does a remodel take?

Real on-site timelines for bathrooms, kitchens and additions, the six stages before and after construction, and what causes delays.

The short answer

Bathrooms in weeks, kitchens in weeks to months, additions in months

Typical on-site construction times on the Eastside: a bathroom 1–6 weeks, a kitchen 3–16 weeks, an addition 1–9 months. Those are build times once the design is final, the permit is issued and materials have arrived — the planning before that is where most schedules are won or lost.

ProjectTypical on-site time
Bathroom refresh1–2 weeks
Hall / guest bathroom remodel2–4 weeks
Primary bathroom remodel4–6 weeks
Kitchen refresh3–4 weeks
Midrange kitchen remodel6–10 weeks
Upscale kitchen / layout change10–16 weeks
Bump-out1–2 months
Room addition3–5 months
Second-story addition6–9 months

Typical ranges from our projects, not a guarantee — your written schedule is set for your project before work starts. Costs for each are on our bathroom, kitchen and addition cost pages.

The whole journey

Six stages from first call to handover

1. Walkthrough and estimate

We visit, measure and send a written, itemized estimate.

2. Design and selections

You choose tile, cabinets, fixtures and finishes. Fast decisions keep the schedule tight.

3. Permits

In Bellevue a remodel that does not touch structure usually gets its permit the same day. Projects with plan review take longer — Bellevue quotes about a three-week turnaround when a simple remodel turns out to need plan review; additions and ADUs can take months.

4. Ordering materials

Custom cabinets, special-order tile and windows can take weeks. We order early so the crew never waits.

5. Construction

Protection first, then demolition, rough-in, inspections and finishes, with a schedule update every week.

6. Punch list and handover

We walk the finished space with you, fix every item on the list and hand over the warranties.

Delays

What slows a remodel down

  • Changing selections after work starts. A new tile or a different vanity can mean re-ordering and re-sequencing trades.
  • Hidden damage behind walls. We document it and price it in writing before continuing.
  • Special-order materials ordered late. The most common — and most avoidable — delay.
  • Structural changes. Engineering and plan review add weeks before construction can begin.

Want to know whether your project needs a permit at all? See what needs a permit on the Eastside, or read how a project runs with us.

Questions

Timeline questions

How long does a bathroom remodel take?
About 1–2 weeks for a refresh, 2–4 weeks for a full hall bathroom and 4–6 weeks for a primary bathroom of on-site work.
How long does a kitchen remodel take?
About 3–4 weeks for a refresh, 6–10 weeks for a midrange remodel and 10–16 weeks for an upscale remodel, once cabinets and materials have arrived.
How long does a home addition take?
About 1–2 months for a bump-out, 3–5 months for a room addition and 6–9 months for a second story, plus time for design and permit review.
How soon can you start?
The start date is confirmed after signing. It depends on design decisions, permit review and material deliveries, and we tell you honestly where each one stands.
Will I get a written schedule?
Yes. You get a schedule before work begins and an update every week during construction.

Sources: City of Bellevue — residential building permits. Checked November 2026.